1. Question:
A vendor developed an excellent quality deliverable. Since
everyone liked it, you want to award the vendor for their efforts. What is the
correct way to document this experience so it is beneficial for future projects
in your organization?
B: Recommend the vendor to other departments in your organization.
C: Recommend the vendor to other departments as well as your friends.
D: Construct a Seller Performance Evaluation.
2. Question: Nathan is a new project manager who has been assigned a project which is in its early stages. He has been given the task to estimate the costs, but limited information is provided to him. Which of the following techniques will not be beneficial to him?
A: Top-down EstimatingB: Analogous Estimating
C: Three Point Estimating
D: Bottom-up Estimating
3. Question: You are using a chart/diagram/technique where you are displaying the amount of work you have completed against the amount of work you need to deliver on a certain date. Which technique are you using to track your project?
A: Earned Value AnalysisB: Iteration Burndown Chart
C: Performance Reviews
D: Trend Analysis
4. Question: Matt has been assigned a new project. As a part of the communication effort, he is documenting the resources, roles and responsibilities, skills required and the reporting relationship. Where should Matt document this information so that project communications can happen most optimally?
A: Resource Management PlanB: RACI Chart
C: Resource Calendar
D: Communication Management Plan
5. Question: Tom and his project management team are taking over a project for their new client. The project was previously handled by another firm. As a part of clean-up effort, Tom and his team are currently inspecting the project deliverables. The team is recording the number and nature of defects found in these deliverables in a defect detail list. The defect details list in this case is an example of?
A: Defect LogB: Work performance data
C: Work performance report
D: Work performance information
6. Question: You are in the initial stages of a project where you have to decide on which project methodology to use. You are in favor of the normal software development life cycle approach; however the SMEs want to do agile methodology instead. Which of the following is not a true statement regarding the generic life cycle of a project?
A: Cost and Staffing Levels are low at the startB: Risk and uncertainty are greatest at the start of the project
C: The ability to influence the final characteristics of the project's product is highest at the start of the project
D: Risk and uncertainty factors do not decrease over the life of the project. It remains constant throughout the project
7. Question: Luis is the project manager. During the contract negotiation process with the selected vendor, Luis decides to issue a contact where he will pay the vendor a set amount for their service. Luis will not take into consideration seller's cost. What is the best description for this type of contract?
A: FP-EPAB: FFP
C: FPIF
D: CPFF
8. Question: Jordan is using a control chart to determine stability of the process and its performance. After developing a new process, he deems that the stability and the performance of the new process is within acceptable limits, and that the process does not need to be adjusted. What are the upper and lower control limits usually set as?
A: + / - 6 sigmaB: + / - 2 sigma
C: + / - 3 sigma
D: + / - 1 sigma
9. Question: Your customer has asked you to establish the scope baseline within next two weeks. Your team is working towards it and is on track. Suddenly, a stakeholder reaches out to you and wants to include a new feature on the project. What should be your next step?
A: Request the stakeholder to follow a formal change control processB: Reject the change
C: Add the feature in your scope
D: Do the impact analysis before issuing a formal change request
10. Question: Jill is at a senior position in the vendor management office. She only gets involved if there is major escalation. It so happens that the team is not happy with the way a vendor is currently working on the project. Jordey, another project manager reaches out to Jill to discuss the performance of the vendor. Which process is Jordey performing?
A: Plan Procurement ManagementB: Control Procurements
C: Conduct Procurements
D: Monitor Risks
11. Question: One of the modules of Tim’s project is to create a social networking platform where the users are posting questions, writing blogs, and reviewing the comments of users. Which technique defines this type of scenario?
A: Information ManagementB: Knowledge Management
C: Expert Judgment
D: Political Awareness
12. Question: You are a project manager. While calculating the estimate, you realize that you will need six resources for six months. You can only get four resources after negotiating with the functional manager and as per the organizational policy, you can hire two more every six months. As a project manager what will be your next step?
A: Hire contractors in accordance with your organizational policy.B: Negotiate with functional manager to get the remaining 2 resources
C: Talk to project sponsor to get more resources
D: Don't do anything and request your assigned resources to fast track the project.
13. Question: While implementing the user interface for the webpage, Alan notices that the required color scheme is too gaudy and does not fit in with the overall look of the website. He decides to use an alternate color scheme that is more appealing to the eye. During testing, the testing team flags this change of the color scheme as a defect. But Alan,disagrees since this doesn’t have any negative implications on the functionality of the webpage. What is your view?
A: Since this was a matter of UI expertise, an expert should be roped in for his opinion. Until, the expert gives his opinion on the matter the testing team should not have flagged this as a defect.
B: Alan did not follow the appropriate change management process when deciding to change the color scheme. Thus, deviating from the original design. Hence, the testing team was correct in flagging this as a defect.
C: This change was a simple matter of changing the color scheme. The change did not affect the functionality in any way. Hence the testing team should not have flagged this as a defect.
D: Alan should have sent an email to the testing team informing of the color change he intended to make. Because the testing team received no prior notice, they were correct in flagging this as a defect.14. Question: Your project is hit by an identified risk and you are in the process of making sure that the team is currently implementing the agreed upon risk response. What process are you currently performing?
A: Plan Risk ResponsesB: Implement Risk Responses
C: Monitor Risks
D: Plan Risk Management
15. Question: You are working on a project where you have outsourced the work to a seller’s company. Based on your discussion with the seller, you are revisiting your project assumptions defined in the scope statement to check whether they are still valid or not. Which process are you currently performing?
A: Monitor RisksB: Control Scope
C: Validate Scope
D: Control Procurement
16. Question: Paul is a project manager. For the last two weeks, he has been receiving lot of escalations from his stakeholders. After evaluating, he finds out that overall project risk has changed. Which process is Paul performing currently?
A: Identify RisksB: Implement Risk Responses
C: Plan Risk Management
D: Monitor Risks
16. Question: Mark is a project manager for an automobile organization. He has to provide the duration estimates to the steering committee. He created the draft schedule after discussing this with the team; however he did not get a chance to conduct a final review before the start of the meeting. What is the best thing to do in such a scenario?
A: Present the estimate to the steering committee as is and tell them that it may be wrong.B: Present the estimate to your senior manager only and then make a decision whether to present it to executive steering committee or not
C: Show the estimate as a rough order of magnitude (ROM)
D: Don't present it to the executive steering committee as it is not accurate.